Stationary UPS Sizing Calculations – Part Seven

 

in Article “Stationary UPS Sizing Calculations – Part Six, we explained the following:

1- Battery Room Design Criteria

2- Ventilation Design Criteria

3- Battery Room Ventilation Calculations:

  • NFPA method,
  • British (metric) units method.

4- Requirement of Air Conditioner for UPS

Today, we will explain the Requirements for UPS Installation and Testing.

 

 

Requirements for UPS Installation

 

 

 

There are (4) major Requirements for UPS Installation:

  1. Location,
  2. Ventilation,
  3. Floor loading capacity,
  4. Floor Space Requirements.

 

 

 

1- Location

 

Preferably the UPS has to be installed close to the loads. If the distance between the load and the UPS is higher, we must consider the voltage drop based on the distance of the cable and suitable action like oversizing the cable needs to be considered.

 

 

 

2- Ventilation

 

Most of the UPSs are designed for a maximum operating temperature of 40°C. The losses of the UPS is dissipated as heat and the UPS room should have the ventilation arrangement to remove the heat to maintain the ambient temperature below 40°C.The ventilation can be in the form of cross ventilation of hot & cold air (using air exchangers-inlet & exhaust fans with suitable filters) or with air conditioner.

It is also possible to install a duct either on the top side or the rear side of the UPS to suck out the heat produced by the UPS.

In order to provide for adequate ventilation, the UPS should be installed in a room, which has at least 1000mm of clearance on the top side or the rear side of the UPS based on the ventilation type. This area of UPS should be cleared of any obstruction, which would impede air flow. Since cooling air enters through a grill at the bottom front/front of the equipment, this area must also be kept clear of any obstructions. 

The UPS room should be relatively free of dust and dirt and other airborne contaminates as heavy layers of dust will reduce the cooling efficiency of the electronic components.

It is important that the room low temperature control be adjusted to maintain the room temperature above the dew point in order to prevent condensation of moisture on the UPS. Also in areas of high humidity, UPS designed to operate under such conditions must be chosen or an adequate dehumidifier or precision air conditioner must be deployed to maintain humidity.

 

However, we explained the Battery Room Ventilation Calculations in article Stationary UPS Sizing Calculations – Part Six

 

 

 

3- Floor loading capacity

 

Care should be taken to assure that the floor loading capacity is sufficient to support the

UPS and batteries. Floor loading of UPS will vary based on the capacity and the type of the UPS. If there is a raised floor, the weight of the entire UPS system may require a concrete base to be installed upon. 

 

 

 

4- Floor Space Requirements

 

It is important that adequate floor space has to be provided for the UPS. Check the dimensional information on the appropriate data sheets from the manufacturers for the floor space requirements.

 

Front Clearance:

A clear area in front of the unit of at least 1meter should be maintained for service personnel.

 

Rear Clearance:

The UPS equipment can be mounted with the back against a wall if rear access is not specifically required; however, if side and rear access can be maintained, it may be helpful should service become necessary.

However, the requirement of rear clearance will be based on the construction of UPS. If the UPS is of modular construction then a rear clearance is mandatory.

 

 

 

4.1- Floor space requirements in design stage

 

In case of design which means that there is no data sheets from the manufacturers for the floor space requirements, the following floor space requirements can be followed:

 

Minimum clearance required will be as per table-1 and fig-1.

 

Clearance Required

Front Suction, Top Throw

Front Suction, Rear Throw

Front Clearance

1000mm

1000mm

Rear Clearance

200mm

1000mm

Side Clearance

200mm

400mm

Top Clearance

1000mm

400mm

 Table-1

Where:

Front Suction, Top Throw: removing air from a space from front and throw it to top side (Top Air Flow)

Front Suction, Rear Throw: removing air from a space from front and throw it to Rear side (Rear Air Flow)

 


Fig.1 Typical Requirement Of Clearance

 

 

 

4.2- Floor space requirements from manufacturers’ data sheets

 

Each manufacturer provide data sheets for his UPS products, from which we can assign the Floor space requirements for each UPS product. Most of the manufactures divide their UPS products into two types of arrangement:

  • UPS with built-in batteries
  • UPS with separated battery cabinets

And of course, the floor space requirements will differ for each arrangement as shown in the below examples:

 

Example#1: Schneider UPS Model Galaxy VS

 


Note#1: This UPS can come with internal batteries or with external batteries.

 


Note#2: dimension of UPS can differ between the one with internal batteries and the one with external batteries.

But the dimensions will not differ for the ones with internal batteries even if the number of internal battery strings changes as shown in below table-2.

 

Table-2



Note#3: the UPS with external batteries, the battery cabinets differ in dimensions based on its type as follows:

  1. Modular battery cabinets
  2. Classic battery cabinets
  3. Galaxy Lithium-ion battery cabinets

Also, the dimensions will not differ for the same model even if the UPS rating changes as shown in below table-3

 

Table-3

Now, the clearance and space flor requirements for a Schneider UPS Model Galaxy VS will be as shown in Fig.2




 Fig.2


Example#2: ABB UPS Model DPA 250

This model has the following requirements:

 


Then the clearance and space flor requirements will be as follows:

 


 

Example#3: ABB UPS Model PowerLine DPA

This model has the following requirements:

 


Then the clearance and space flor requirements will be as follows:

 


 

Example#4: ABB UPS Model SG Series

This model has the following requirements:

 

Then the clearance and space flor requirements will be as follows:

 


 

Example#5: ABB UPS Model MegaFlex DPA

This model has the following requirements:

 


Then the clearance and space flor requirements will be as follows:

 


Example#6: ABB UPS Model PowerScale 33

This model has the following requirements:

 


Then the clearance and space flor requirements will be as follows:


 

 

 

 

UPS Controls, Instruments, Alarms and Indicating Devices

 

 

 

1- UPS Controls

 

The basic UPS system shall contain as a minimum the following control devices:

  • AC input disconnecting device,
  • DC input disconnecting device,
  • UPS output disconnecting device.

For UPS systems utilizing a static transfer switch, the UPS system shall include a control device to manually initiate forward and reverse transfer of the static switch. Control logic for automatic operation of the transfer switch shall be defined for individual applications.

 

 

 

2- UPS Instruments

 

Meters having a full-scale accuracy of ±2% shall be provided to display the following parameters:

  • Inverter input dc voltage,
  • AC alternate (bypass) source voltage,
  • Rectifier output dc current,
  • UPS output ac voltage,
  • UPS output ac,
  • Inverter output frequency.

 

 

 

3- UPS Alarms

 

Alarms should be provided to indicate the following UPS system malfunctions:

  • Loss of Synchronization: Inverter not synchronized to alternate ac source or alternate ac source not available.
  • Low-Inverter Voltage: Inverter ac output voltage is less than 90% of nominal (adjustable).
  • Protective Device Actuation: Indication of protective device operation in the UPS system.
  • DC Bus Undervoltage: Inverter dc input voltage is less than specified minimum.
  • Overload: UPS load current is greater than 100% of rated UPS current.
  • Reverse Transfer: Load is supplied by the alternate ac source.
  • Cooling Trouble: Indication of loss of air-flow through cooling fan.
  • Alternate AC Source Trouble: Alternate ac source is outside specified range.
  •  DC Operation: Alarms when battery current flows to the inverter.

 

 

 

4- UPS Indicating Devices

 

Indicators should be provided to indicate the following status conditions:

  • AC input disconnect device position,
  • DC input disconnect device position,
  • Static transfer switch position,
  • Output disconnect device position.

 

 

 

 

UPS Testing Requirements

 

 

 

UPS shall be design tested and routine tested in the factory. Supplemental tests with actual batteries and load may be required to be performed at the site as follows:

  • First: Functional Unit Tests
  • Second:  Monitor and Control Equipment Routine tests
  • Third: UPS Tests

 

 

 

First: Functional Unit Tests

 

Functional unit tests may be specified in addition to the UPS tests and includes:

  • Rectifier/Charger Tests,
  • Inverter Tests,
  • Transfer-Switch Tests.

 

A- Rectifier/Charger Tests

Rectifier/ charger tests shall be performed according to NEMA PE5. Routine tests shall cover dielectric test, light-load test, and a checking of auxiliary protection devices and control systems.


B- Inverter Tests

In addition to the manufacturer's design and routine tests the optional tests shown in Table-4 shall apply

 

Table-4


C- Transfer-Switch Tests

 

C.1- Tests of UPS transfer switches shall be performed in accordance with IEC Publication 146 and IEC Publication 146-2, where applicable.  The following routine tests shall be performed:

  • Dielectric/insulation
  • Auxiliary devices check
  • Protective devices check
  • Supervisor and remote signal circuits check
  • Light-load transfer test

 

C.2- Design testing of UPS transfer switches shall require a functional test with a complete UPS. In addition to the tests listed in 7.2.3.1 a design test program shall include:

  • Complete functional test, for example, switching of loads
  • Transfer time test
  • Load test, temperature rise
  • Short-time overload
  • Short-circuit capability

 

 

 

Second:  Monitor and Control Equipment Routine tests

 

These tests shall include the following tests:

  • Dielectric/insulation
  • Electric circuit check

Operation control check Design tests shall not be required for monitor and control equipment.

 

 

 

Third: UPS Tests

 

The complete UPS testing in accordance with Table-5 shall be performed at the factory after assembly and interconnection of the functional units. These tests shall be followed by supplemental tests at the site.

Table-5

 

 

 

Test Specifications

 

The following (13) tests, when conducted at the site, shall use the maximum available load, which does not exceed the rated continuous load, under the following conditions:

  • With and without bypass, where appropriate
  • With and without redundancy, where appropriate

 

1- Light-Load Test

This test shall be performed to verify that the UPS is correctly connected and all functions operate properly. The following tests shall be performed:

  • Output voltage and frequency
  • The operation of all control switches, measuring devices, meters, and other means required to determine proper UPS operation.

 

2- Synchronization Test

This test shall be required for UPS systems when synchronization with an alternate source is required. Variation frequency limits shall be tested by use of a variable-frequency generator. The rate of change of frequency during synchronization and the UPS output voltage shall be measured.

 

3- AC Input Failure Test

The test shall be performed by interrupting the ac input power or shall be simulated by switching off all UPS rectifiers and bypass feeders at the same time. Output-voltage variations shall be checked for specified limits. Variation frequency shall be observed.

This test shall be performed with dc source available.

 

4- AC Input Return Test

This test shall be performed either by restoring the ac input power or simulated by switching on all UPS rectifiers and bypass feeders at the same time. Proper operation of the UPS rectifier shall be observed. AC output voltage and frequency shall also be recorded.

 

5- Transfer Test—Forward and Reverse

This test shall be required for UPS systems that have a static bypass switch. Transients, such as maximum and minimum voltages, and transfer times shall be measured during load transfer to and from the bypass source.

 

6- Rated Full-Load Test

Load tests shall be performed by connecting loads to the UPS output, equivalent to the full-rated load at the extremes of ac and dc input-voltage range.

 

7- UPS Efficiency Test

UPS efficiency at rated capacity shall be determined by the measurement of the real-power input and real-power output of the UPS system or shall be derived from the results of individual UPS unit tests.

 

8- Output-Voltage Balance Test

For three-phase systems the UPS phase-to-phase and phase-to-neutral output voltages shall be recorded during the following tests:

  • Symmetrical load conditions
  • Imbalanced load conditions from no load to full load Phase angle deviations shall be recorded, or derived by calculation from the values of phase-to-phase and phase-toneutral voltages.

 

9- Overload Capability Test

The values of overload(s) sequences shall be applied for the time interval(s) specified. Values of voltage and current shall be observed.

 

10- Short-Circuit Capability Test

A short circuit shall be applied to the UPS output and the following information shall be recorded for a UPS with and without bypass:

  • The operation of protective devices or circuits
  • The short-circuit current as function of time
  • Appropriate circuit protective devices (fuses, circuit breakers) shall be permitted to be applied when making these tests.

 

11- Harmonic-Components Test

Harmonic components of output voltage shall be recorded under rated linear (sine wave) and nonlinear load conditions.

 

12- Audible Noise Test

For test procedure and limits, the manufacturer should be consulted. Audible noise of a complete UPS may differ considerably from the values of individual functional units. Room conditions—resonance and reflection—will cause differences from calculated or measured values.

 

13- Heat-Load Test

The UPS shall be operated in those modes that would result in the greatest heat generation to verify acceptable component operating temperatures.

 

 

This is the end of this course.


Subject Of Pervious Article

Article

Applicable Standards for UPS Systems

What is a UPS?

Why do we need a UPS?

UPS Rating

Classification of UPS:

1-Voltage range,

2-No. of phases,

3- Mobility,

4- Technological design,

Classification and Types of UPS – Part One

5- Physical Size/capacity,

6- Form factor/ configurations:

6.1- “N” System Configuration

Classification and Types of UPS – Part Two

6.2- “N+1” System Configuration, which includes:

  • Isolated Redundant Configuration (N +1)
  • Parallel Redundant Configuration (1+1)
  • Parallel Redundant Configuration (N +1)
  • Parallel Redundant Configuration (N +2) and so on

6.3- Parallel Redundant with Dual Bus Configuration (N+1 or 1+1)

Classification and Types of UPS – Part Three

 

 

6.4- Parallel Redundant with STS Configuration

  • Parallel Redundant Configuration (1+1) + STS
  • Parallel Redundant Configuration (N+1) + STS

6.5- System plus System 2(N+1), 2N+2, [(N+1) + (N+1)], and 2N

Classification and Types of UPS – Part Four

 

 

 

7- According to UPS Topology

7.1 Off-line or Standby UPS,

7.2 Line Interactive UPS,

7.3 Standby-Ferro UPS,

7.4 Online Double Conversion UPS,

7.5 The Delta Conversion On-Line UPS.

Classification and Types of UPS – Part Five

 

 

 

8- According to UPS Distribution Architecture

8.1 Centralized UPS Configuration,

8.2 Distributed (Decentralized) UPS Configuration,

8.2.1 Distributed UPS-Zonewise Configuration

8.3 Hybrid UPS Configuration.

Conventional (Monolithic) Vs Modular UPS System:

  • Deploy UPSs in parallel,
  • Deploy UPSs in Series,
  • Use modular UPS products.

Classification and Types of UPS – Part Six

 

 

Three Basic Configurations Of Mains And Bypass For A UPS System:

  • Single mains,
  • Single mains without bypass,
  • Dual mains.

9-According to Use of transformers with the UPS:

  • Transformer based,
  • Transformer less UPS,
  • Transformer less UPS with external input/ output transformer.

Classification and Types of UPS – Part Seven

 

 

 

Transformer Arrangements in Practical UPS Systems:

1-Transformer options for the “single mains” configuration

2-Transformer Options for the “Dual Mains” Configuration

Classification and Types of UPS – Part Eight

 

 

3- Transformer options for “single mains without bypass”

Classification and Types of UPS – Part Nine

Components of Online Double Conversion UPS:

1- Rectifier,

2- Inverter,

3- Energy Storage system:

3.1 Battery

Components of Online Double Conversion UPS– Part One

 

 

 

3.1.1 Battery Configurations

Serial Strings,

Parallel Strings.

3.1.2 Battery Size and Location

3.1.3 Battery Transition Boxes

3.1.4 Battery Monitoring

3.2 Energy Storage System – Flywheel

3.3 Energy Storage system – Super Capacitors

3.4 Hydrogen Fuel Cells

4- Static switch

Earthing Principles of UPS Systems

Components of Online Double Conversion UPS – Part Two

 

 

Evaluation Criteria for Selecting an UPS

 

Evaluation Criteria for Selecting an UPS-Part One

Example: Selecting an Uninterruptible Power Supply (UPS)

UPS System Ratings and Service Conditions

First: from IEC 60146-4

Second: according to American standards

Evaluation Criteria for Selecting an UPS-Part Two

 

 

The UPS sizing calculations steps

Stationary UPS Sizing Calculations – Part One

 

2- Rectifier/Charger Sizing Calculations

3- Inverter sizing calculations & Static Switch Sizing

4- The Battery sizing calculations

First: The Manufacturers’ methods, which include:

  • Method#1:Watts per cell method
  • Method#2:Watts per bank method
  • Method#3:Ampere per cell method

Stationary UPS Sizing Calculations – Part Two

 

 

 

 

Second: The IEEE methods of Battery Sizing Calculations which includes:

  • Method#1: The IEEE 485 method,
  • Method#2: The IEEE 1184 method.

Stationary UPS Sizing Calculations -Part Three

 

 

- UPS Backup time calculation

- Selection and sizing of UPS protective devices (CBs or Fuses)

Stationary UPS Sizing Calculations – Part Four


Selection of UPS Cables

Sizing of UPS Cables:

  • UPS Input Cables,
  • UPS Output Cables,
  • Neutral Conductors,
  • UPS to Battery Cables.

Sizing a generator set for UPS system

Stationary UPS Sizing Calculations – Part Five


Battery Room Design Criteria

Ventilation Design Criteria

Battery Room Ventilation Calculations:

  • NFPA method,
  • British (metric) units method.

Requirement of Air Conditioner for UPS

Stationary UPS Sizing Calculations – Part Six


 

 

 

No comments:

Post a Comment