in Article “Stationary UPS Sizing Calculations – Part Six”, we explained the following:
1- Battery
Room Design Criteria
2- Ventilation
Design Criteria
3- Battery
Room Ventilation Calculations:
- NFPA method,
- British (metric) units method.
4- Requirement
of Air Conditioner for UPS
Today, we
will explain the Requirements
for UPS Installation and Testing.
Requirements
for UPS Installation |
There are (4) major Requirements for UPS
Installation:
|
1- Location Preferably
the UPS has to be installed close to the loads. If the distance between the
load and the UPS is higher, we must consider the voltage drop based on the
distance of the cable and suitable action like oversizing the cable needs to
be considered. |
2- Ventilation Most
of the UPSs are designed for a maximum operating temperature of 40°C. The
losses of the UPS is dissipated as heat and the UPS room should have the
ventilation arrangement to remove the heat to maintain the ambient
temperature below 40°C.The ventilation can be in the form of cross
ventilation of hot & cold air (using air exchangers-inlet & exhaust
fans with suitable filters) or with air conditioner. It is also possible to install a duct either on the top side or the rear side of the UPS to suck out the heat produced by the UPS. In order to provide for adequate ventilation, the UPS should be installed in a room, which has at least 1000mm of clearance on the top side or the rear side of the UPS based on the ventilation type. This area of UPS should be cleared of any obstruction, which would impede air flow. Since cooling air enters through a grill at the bottom front/front of the equipment, this area must also be kept clear of any obstructions. The UPS room should be relatively free of dust and dirt and other airborne contaminates as heavy layers of dust will reduce the cooling efficiency of the electronic components. It
is important that the room low temperature control be adjusted to maintain
the room temperature above the dew point in order to prevent condensation of
moisture on the UPS. Also in areas of high humidity, UPS designed to operate
under such conditions must be chosen or an adequate dehumidifier or precision
air conditioner must be deployed to maintain humidity. However, we explained the Battery Room Ventilation Calculations in article “Stationary UPS Sizing Calculations – Part Six”
|
3- Floor loading capacity Care
should be taken to assure that the floor loading capacity is sufficient to
support the UPS
and batteries. Floor loading of UPS will vary based on the capacity and the
type of the UPS. If there is a
raised floor, the weight of the entire UPS system may require a concrete base to be
installed upon. |
4- Floor Space Requirements It
is important that adequate floor space has to be provided for the UPS. Check
the dimensional information on the appropriate data sheets from the
manufacturers for the floor space requirements. Front
Clearance: A
clear area in front of the unit of at least 1meter should be maintained for
service personnel. Rear
Clearance: The
UPS equipment can be mounted with the back against a wall if rear access is
not specifically required; however, if side and rear access can be
maintained, it may be helpful should service become necessary. However,
the requirement of rear clearance will be based on the construction of UPS.
If the UPS is of modular construction then a rear clearance is mandatory. |
4.1- Floor space requirements in
design stage In
case of design which means that there is no data sheets from the
manufacturers for the floor space requirements, the following floor space
requirements can be followed: Minimum
clearance required will be as per table-1 and fig-1.
Where: Front
Suction, Top Throw:
removing air from a space from front and throw it to top side (Top Air Flow) Front
Suction, Rear Throw: removing air from a space
from front and throw it to Rear side (Rear Air Flow) Fig.1 Typical
Requirement Of Clearance |
4.2- Floor space requirements from
manufacturers’ data sheets Each manufacturer provide data sheets for his UPS products, from which we can assign the Floor space requirements for each UPS product. Most of the manufactures divide their UPS products into two types of arrangement:
And
of course, the floor space requirements will differ for each arrangement as
shown in the below examples: Example#1:
Schneider UPS Model Galaxy VS Note#1:
This UPS can come with internal batteries or with external batteries. Note#2:
dimension of UPS can differ between the one with internal batteries and the
one with external batteries. But the dimensions will not differ for the ones with internal batteries even if the number of internal battery strings changes as shown in below table-2. Table-2
Note#3:
the UPS with external batteries, the battery cabinets differ in dimensions
based on its type as follows:
Also,
the dimensions will not differ for the same model even if the UPS rating changes
as shown in below table-3 Table-3 Now,
the clearance and space flor requirements for a Schneider UPS Model Galaxy VS
will be as shown in Fig.2 Example#2:
ABB UPS Model DPA 250 This model has the following requirements: Then
the clearance and space flor requirements will be as follows: Example#3: ABB UPS Model PowerLine DPA This model has the following requirements: Then
the clearance and space flor requirements will be as follows: Example#4:
ABB UPS Model SG Series This model has the following requirements: Then
the clearance and space flor requirements will be as follows: Example#5: ABB UPS Model MegaFlex DPA This model has the following requirements: Then
the clearance and space flor requirements will be as follows: Example#6: ABB UPS Model PowerScale 33 This model has the following requirements: Then
the clearance and space flor requirements will be as follows: |
UPS Controls, Instruments, Alarms and Indicating Devices |
1- UPS Controls The basic UPS system shall contain as a minimum the following control devices:
For UPS systems utilizing a static
transfer switch, the UPS system shall include a control device to manually
initiate forward and reverse transfer of the static switch. Control logic for
automatic operation of the transfer switch shall be defined for individual
applications. |
2- UPS Instruments Meters having a full-scale accuracy of ±2% shall be provided to display the following parameters:
|
3- UPS Alarms Alarms should be provided to
indicate the following UPS system malfunctions:
|
4- UPS Indicating
Devices Indicators should be provided to
indicate the following status conditions:
|
UPS Testing Requirements |
UPS shall be design tested and routine tested in the factory. Supplemental tests with actual batteries and load may be required to be performed at the site as follows:
|
First:
Functional Unit Tests Functional unit tests may be
specified in addition to the UPS tests and includes:
A- Rectifier/Charger Tests Rectifier/ charger tests shall be
performed according to NEMA PE5. Routine tests shall cover dielectric test,
light-load test, and a checking of auxiliary protection devices and control
systems. B- Inverter Tests In addition to the manufacturer's
design and routine tests the
optional tests shown in Table-4 shall apply Table-4 C- Transfer-Switch Tests C.1- Tests of UPS transfer switches
shall be performed in accordance with IEC Publication 146 and IEC Publication
146-2, where applicable. The following
routine tests shall be performed:
C.2- Design testing of UPS transfer
switches shall require a functional test with a complete UPS. In addition to
the tests listed in 7.2.3.1 a design test program shall include:
|
Second: Monitor and Control Equipment Routine tests These tests shall include the following tests:
Operation control check Design tests
shall not be required for monitor and control equipment. |
Third:
UPS Tests The complete UPS testing in accordance with Table-5
shall be performed at the factory after assembly and interconnection of the
functional units. These tests shall be followed by supplemental tests at the
site. Table-5 |
Test
Specifications The following (13) tests, when conducted at the site, shall use the maximum available load, which does not exceed the rated continuous load, under the following conditions:
1- Light-Load Test This test shall be performed to
verify that the UPS is correctly connected and all functions operate
properly. The following tests shall be performed:
2- Synchronization Test This test shall be required for UPS
systems when synchronization with an alternate source is required. Variation
frequency limits shall be tested by use of a variable-frequency generator.
The rate of change of frequency during synchronization and the UPS output
voltage shall be measured. 3- AC Input Failure Test The test shall be performed by
interrupting the ac input power or shall be simulated by switching off all
UPS rectifiers and bypass feeders at the same time. Output-voltage variations
shall be checked for specified limits. Variation frequency shall be observed. This test shall be performed with dc
source available. 4- AC Input Return Test This test shall be performed either
by restoring the ac input power or simulated by switching on all UPS
rectifiers and bypass feeders at the same time. Proper operation of the UPS
rectifier shall be observed. AC output voltage and frequency shall also be
recorded. 5- Transfer Test—Forward and Reverse
This test shall be required for UPS
systems that have a static bypass switch. Transients, such as maximum and
minimum voltages, and transfer times shall be measured during load transfer
to and from the bypass source. 6- Rated Full-Load Test Load tests shall be performed by
connecting loads to the UPS output, equivalent to the full-rated load at the
extremes of ac and dc input-voltage range. 7- UPS Efficiency Test UPS efficiency at rated capacity
shall be determined by the measurement of the real-power input and real-power
output of the UPS system or shall be derived from the results of individual
UPS unit tests. 8- Output-Voltage Balance Test For three-phase systems the UPS phase-to-phase and phase-to-neutral output voltages shall be recorded during the following tests:
9- Overload Capability Test The values of overload(s) sequences
shall be applied for the time interval(s) specified. Values of voltage and current
shall be observed. 10- Short-Circuit Capability Test A short circuit shall be applied to the UPS output and the following information shall be recorded for a UPS with and without bypass:
11- Harmonic-Components Test Harmonic components of output
voltage shall be recorded under rated linear (sine wave) and nonlinear load
conditions. 12- Audible Noise Test For test procedure and limits, the
manufacturer should be consulted. Audible noise of a complete UPS may differ considerably
from the values of individual functional units. Room conditions—resonance and
reflection—will cause differences from calculated or measured values. 13- Heat-Load Test The UPS shall be operated in those
modes that would result in the greatest heat generation to verify acceptable
component operating temperatures. |
This is the end of this course.
Subject
Of Pervious Article |
Article |
Applicable Standards for UPS Systems What is a UPS? Why do we need a UPS? UPS Rating Classification of UPS: 1-Voltage range, 2-No. of phases, 3- Mobility, 4- Technological design, |
|
5- Physical Size/capacity, 6- Form factor/ configurations: 6.1- “N” System Configuration |
|
6.2- “N+1” System Configuration, which
includes:
6.3- Parallel Redundant with Dual Bus Configuration
(N+1 or 1+1) |
Classification and Types of UPS –
Part Three |
6.4- Parallel Redundant with STS Configuration
6.5- System plus System 2(N+1), 2N+2, [(N+1) + (N+1)],
and 2N |
Classification and Types of UPS –
Part Four |
7- According to UPS Topology 7.1
Off-line or Standby UPS, 7.2 Line
Interactive UPS, 7.3
Standby-Ferro UPS, 7.4 Online
Double Conversion UPS, 7.5 The
Delta Conversion On-Line UPS. |
Classification and Types of UPS –
Part Five |
8- According to UPS Distribution Architecture 8.1 Centralized UPS Configuration, 8.2 Distributed (Decentralized) UPS
Configuration, 8.2.1 Distributed UPS-Zonewise
Configuration 8.3 Hybrid UPS Configuration. Conventional (Monolithic) Vs Modular UPS System:
|
Classification and Types of UPS –
Part Six |
Three Basic Configurations Of Mains
And Bypass For A UPS System:
9-According to Use of transformers
with the UPS:
|
Classification and Types of UPS –
Part Seven |
Transformer Arrangements in Practical UPS Systems: 1-Transformer options for the “single mains”
configuration 2-Transformer Options for the “Dual Mains” Configuration |
Classification and Types of UPS –
Part Eight |
3- Transformer options for “single mains without
bypass” |
|
Components of Online Double Conversion UPS: 1- Rectifier, 2- Inverter, 3- Energy Storage system: 3.1 Battery |
Components of
Online Double Conversion UPS– Part One
|
3.1.1 Battery Configurations Serial Strings, Parallel Strings. 3.1.2 Battery Size and Location 3.1.3 Battery Transition Boxes 3.1.4 Battery Monitoring 3.2 Energy Storage System – Flywheel 3.3 Energy Storage system – Super Capacitors 3.4 Hydrogen Fuel Cells 4- Static switch Earthing Principles of UPS Systems |
Components of Online Double
Conversion UPS – Part Two |
Evaluation Criteria for Selecting an UPS |
Evaluation Criteria
for Selecting an UPS-Part One
|
Example: Selecting an Uninterruptible Power Supply
(UPS) UPS System Ratings and Service Conditions First: from IEC 60146-4 Second: according to American
standards |
Evaluation Criteria for Selecting an
UPS-Part Two |
The UPS sizing calculations steps |
Stationary UPS
Sizing Calculations – Part One
|
2- Rectifier/Charger Sizing Calculations 3- Inverter sizing calculations & Static Switch
Sizing 4- The Battery sizing calculations First: The Manufacturers’ methods, which include:
|
Stationary UPS Sizing Calculations –
Part Two |
Second: The IEEE methods of Battery Sizing Calculations
which includes:
|
Stationary UPS Sizing Calculations
-Part Three |
- UPS Backup time calculation - Selection and sizing of UPS protective devices (CBs or Fuses) |
Stationary UPS Sizing Calculations – Part Four |
Selection of UPS Cables Sizing of UPS Cables:
Sizing a generator set for UPS system |
Stationary UPS Sizing Calculations – Part Five |
Battery Room Design Criteria Ventilation Design Criteria Battery Room Ventilation
Calculations:
Requirement of Air Conditioner for
UPS |
Stationary UPS Sizing Calculations – Part Six |
No comments:
Post a Comment