Stationary UPS Sizing Calculations – Part Two


As we stated in the previous article “Stationary UPS Sizing Calculations -Part One”, That Stationary UPS Sizing Calculations include:

  1. The UPS sizing calculations,
  2. Rectifier sizing calculations,
  3. Inverter sizing calculations,
  4. The Battery sizing calculations.

We explained the UPS sizing calculations in the above article and Today, we will explain the other calculations.

 

 

 

2- Rectifier/Charger Sizing Calculations

 

 

 

The rectifier should be properly sized to satisfactorily perform these two tasks: 

  1. Supply the inverter at full load (Ir) and
  2. Charge the batteries at the maximum charge current (Ic).

 

Therefore, the rectifier DC load current (Idc) is the sum of Ir and Ic. In equation form:

Idc = Ir + Ic

The inverter design DC full load current (Ir) can be computed as follows:

Ir = S/Vdc

Where:

Ir = Design DC full load current (A), the design DC load current is the current drawn by the inverter from the rectifier at full load.

S = the selected UPS VA rating

Vdc = nominal battery / DC link voltage

 

Meanwhile, the maximum battery charging current can be computed as follows:

Ic = (C X f)/t

Where:

Ic = maximum DC charge current (A)

C = selected battery capacity (Ampere-hour or Ah)

f = battery recharge efficiency/Loss Factor (typically 1.1)

t = minimum battery recharge time (hours)

 

Example#1:

1000 VA UPS with 60 Ah battery and recharge time of 2.25 hours and nominal battery voltage 120V. Calculate the Rectifier Size.

Solution:

Ir = S/Vdc

Ir = 1000 VA / 120 V = 8.33 A.

 

Ic = (C X f)/t

Ic = (60 Ah X 1.1) / 2.25

Ic = 29.33 A

Thus, the total minimum DC rectifier/charger current is:

Idc = 8.33 + 29.33 = 37.7 A

Select the next standard rectifier rating that exceeds the total minimum DC current above.

Use a 40-Ampere Rectifier.

 

 

 

 

Another Calculation Method

 

Charger size in Amps Ic = Ii+ Ia+ (Ib x Td x K)/ Tr

 

Where:

Ii = Inverter Current Required = Inverter VA x Power Factor/ DC to AC Efficiency/ Float Voltage

Ia = Any additional DC Loads in amperes

Ib = Battery Current Required = Inverter VA x Power Factor/ DC to AC Efficiency/ DCV

Td = Battery Discharge (Run) Time in hours

Tr = Battery Recharge Time in hours

 

Example#2:

Determine the charger required for a 20kVA UPS with a 60 cell lead acid battery, no additional DC loads, 1 Hour backup and 8 hour recharge time.

 

Solution:

Charger size in Amps Ic = Ii+ Ia+ (Ib x Td x K)/ Tr

Ii = 20,000VA x 0.8 PF/0.86/130 V = 143A

la = 0

Ib = 20,000VA x 0.8 PF/0.86/109 V = 171A

Then:

Ic= 143A + 0+171A x 1Hr x 1.15/8Hr = 143+24.6 = 167.6Amps

 

 

 

 

3- Inverter sizing calculations

 

 

 

The inverter must be rated to continuously supply the UPS loads. Therefore, the inverter shall be sized based on the selected UPS VA rating.

For a three-phase UPS:

Iac = S / (1.732 X Vo)

For a single-phase UPS:

Iac = S/Vo

 

Where:

Iac = design AC full load current (A)

S = UPS VA rating

Vo = nominal AC output voltage (line-to-line voltage for a three phase UPS)

 

Example#3:

A single-phase 1000 VA UPS and nominal UPS voltage 120V. Calculate inverter size.

 

Solution:

For a single-phase UPS:

Iac = S/Vo

Iac = 1000 VA / 120 V

Iac = 8.33 A

Select the next standard inverter rating that exceeds the design AC load current.

Use a 10-Ampere Inverter.

 

 

 

 

Static Switch Sizing

 

 

 

Like the inverter, the static switch must be rated to continuously supply the UPS loads. Therefore, the static switch can be sized using the design AC load current (as above for the inverter sizing)

 

 

 

 

4- The Battery sizing calculations

 

 



Importance of Battery Sizing calculation

Battery sizing calculation is very important for the following reasons:

  • In order to ascertain that it can supply power to the connected loads for the time period it is designed.
  • Unsuitable sizing of the battery can pose many serious problems such as permanent battery damage because of over-discharge, low voltages to the load, insufficient backup times.

 

 

 

 


Important terms for UPS Battery sizing

(1) Discharge rate:

For an UPS system battery, the discharge rate should correspond to the highest inverter input power required to produce rated output at minimum input dc voltage.

The end of discharge voltage should be equal to or higher than the minimum dc input voltage required by the inverter to maintain rated performance.

The minimum dc voltage required by the inverter is normally published by the manufacturer. The maximum dc power required by the inverter can be obtained from the manufacturer or can be calculated. In addition, it is recommended to include a margin of 30 percent for the required capacity to account for load growth and battery aging.

 

(2) Lifetime:

The expected lifetime of batteries on UPS duty is usually stated in terms of years of service on continuous charge to an end of life defined as the failure to be able to deliver a certain percentage of rated capacity. Initial capacity (unless specified as 100 percent capacity) is usually in the range of 90 to 95 percent of rated capacity. This will rise to 100 percent capacity in normal service after several charge-discharge cycles.

IEEE 450 recommends that a battery be replaced when its actual capacity drops to 80 percent of rated capacity; however, some manufacturers rate "end-of-life" at 50 percent of rated capacity. Obviously, the user needs to check the initial capacity rating, the service life period, and the aging characteristics given in the battery guarantee so as not to be unpleasantly surprised.

 

 


(3) End of discharge voltage:

UPS batteries are not sized on so many ampere-hours of capacity for an 8-hour period. Battery voltage is not constant, so if the load requires a constant power output, which most UPS applications do, the current must increase as the voltage decreases. Consequently, the battery is sized to supply a specific kW rate (usually the maximum inverter kW requirement without recharging) for a specific period of time (usually 5 to 15 minutes) to a minimum specific end voltage and, for lead-acid types, at a maximum specific gravity (measured at 77°F).

 

(3)(a) Lead-acid cells

A nominal system design may utilize minimum end voltage of

1.67 to 1.75 volts per cell and a maximum specific gravity of 1.215 at 77°F. The actual end voltage should be the voltage which the UPS manufacturer, battery manufacturer, or the system design requires, whichever is higher. In some cases, designs provide higher end voltages to meet design concerns. A higher specific gravity may result in a battery installation needing less space, but results in shorter life spans and higher cell losses and float voltages. The lower end voltage that manufacturers recommend may cause the UPS to go to static bypass or, by overstressing battery plates, shorten the life of the battery.

 

(3)(b) Nickel-cadmium (ni-cad) cells:

A nominal system design for ni-cad units will be to a minimum end voltage of 1.14 volts at 77°F with the actual end voltage to meet both manufacturers' and system design requirements. The specific gravity of a new cell will vary between 1.160 and 1.190 at 77°F, depending upon the manufacturer. Lower specific gravities are generally used in cells with larger electrolyte reserves. Higher specific gravities are typically used for low-temperature applications. The specific gravity will decrease slowly over the years because of evaporation and other effects, even though the surface of the electrolyte is probably covered with a protective layer of oil. Renewal will be necessary if the specific gravity decreases to 1.130 to 1.160, depending upon the manufacturer's instructions.

 

(3)(c) Temperature correction:

Ratings are at 77°F (25°C). Therefore, to determine specific gravity, which is temperature sensitive, a temperature correction factor must be applied.

For both lead-acid and nickel-cad batteries, add one point (.001) to the hydrometer reading for every 3°F above 77°F and subtract one point for every 3°F below 77°F.

The battery is rated in watts/cell at an ambient temperature of 25-27deg C. When the operating temperature or battery is less the capacity of the battery will be reduced and when the temperature is higher than the design temperature, the capacity of the battery increases.

Elevated temperature operation will shorten battery life. A general rule of thumb for lead-acid batteries is that the prolonged use at elevated temperatures will reduce the battery life by approximately 50% for every 8 ºC above 25 ºC

 


(4) Ambient temperature:

The usual controlled environment provided for batteries should eliminate temperature correction while a 100 percent UPS inverter capacity normally allows an adequate kW design margin. The life of a battery in comparison with an UPS system (which may be outdated and replaced in much less time) may mean that the aging factor is not of such great importance.

 

(5) Battery protection time:

Battery protection time depends on the load type and functions. Generally, a battery with a minimum protection time of one minute is necessary for the initial operation of the inverter without support from the power supply source, i.e., during the walk-in time. There is no upper limit for the protection time.

However, other considerations may limit the length of battery protection time. Examples are the loss of the environmental control support, which could limit the length of a computer operation time with power loss to 5, 10, or 15 minutes. In such a case, there is no need to select a battery protection time which can extend computer operating time beyond the time for which a computer system can operate before it must shutdown due to overheating.

The battery protection time shall not be less than one minute and shall not exceed the maximum time the load can be operated with the loss of the environmental support equipment as specified by the equipment manufacturer (normally in the range of 1 to 15 minutes).

 

(6) Battery Back-up time or Autonomy Time or discharge time:

This is the time that the battery must support the load and is often called autonomy or discharge time – typical systems are sized for 5 to 10 minutes autonomy.

Battery manufacturers supply run-time charts that can be used by knowledgeable persons to calculate the run time given in your specific situation.

 

For certain application, Consider the following solution scenarios for Battery Back-up time:

  • UPS with 10-15 minutes of runtime and no generator 

This solution allows time to safely shut down connected equipment and save work-in-progress.

  • UPS with 10-15 minutes of runtime and a generator 

This solution will keep connected systems up and running until the generator powers on.

  • UPS with two or more hours of battery runtime 

In some cases, generators may not be practical and organizations that wish to remain up and running during an extended outage must rely solely on UPS batteries

 

 

 

 

Common Battery types used in UPS systems

 

Typically the following battery types are used in UPS systems:

  • Lead Acid/Plante Battery
  • Lead Acid/Antimony Battery
  • Lead Acid/Calcium Battery
  • Lead Acid/Calcium, Maintenance-free Liquid Electrolyte Battery
  • Lead Acid/Calcium, Maintenance-free Gelled Electrolyte, Sealed Battery
  • Lead Acid (Special Alloy), Suspended Electrolyte, Maintenance-free, Sealed Battery
  • Nickel Cadmium, Pocket Plate Liquid Electrolyte Battery

 

 

 

 

Relations between battery cells, battery, battery bank, battery block & battery string

 

Batteries consists of nos. Of cells in series (total battery voltage = nos. of cells * cell voltage)

Common battery configurations:

  • 1 cell: 2 V
  • 3 cells: 6 V
  • 6 cells: 12 V

 

Note: Multiple batteries can be connected in series for higher system voltage

 

  • Battery block refers to a complete individual battery (block = battery)
  • Battery string is a group of batteries (blocks) connected in series or parallel
  • A battery bank is a group of batteries or strings connected together for a single application in parallel

 

From above, when you Select the Battery Type (nos. of cells per battery)

Then,

Nos. of batteries = Total nos. of cells / nos. of cells per battery

Total battery voltage = nos. of cells * cell voltage

W per battery = W per cell * nos. of cells per battery

W per battery = Battery Total load (W) / Nos. of batteries

W per String = W per battery * nos. of batteries per string

Nos. of strings required = Adjusted Battery Load in W per Battery / Watts the battery can deliver          (from battery manufacturer datasheet)

 

 

 

 

Methods for UPS Battery Sizing

 

 

 

Various methods exist to enable the correct selection of batteries for UPS applications, these methods are:

 

First: The Manufacturers’ methods, which include:

  • Method#1:Watts per cell method
  • Method#2:Watts per bank method
  • Method#3:Ampere per cell method

 

Second: The IEEE methods, which include:

  • Method#1:The IEEE 485 method
  • Method#2:The IEEE 1184 method

 

The battery sizing can be initiated once we have the following information:

  1. Loads need to be supported by battery
  2. Minimal voltage for battery (end of discharge voltage)
  3. Back up time(s)
  4. ambient temperature

 

 

 

 

First: The Manufacturers’ Methods

 

 

 

 

Method#1: Watts per cell method

 

Normally information supplied for lead acid batteries designed for short discharge times (5-120 minutes) is in the form of kilowatts per cell tabulated for various back-up times. The required [Watts] per cell are given by:

W per cell = AS + (VA x PF)/ (EFF x Number Of Cells)

 

Where:

AS = Additional loads expressed in amperes

VA = VA of the load or UPS

PF = Power factor of load

EFF = Efficiency of the UPS at the given load

No. Cells = Number of cells required.

 

Example#4:

Select the battery model number and quantity (using the typical watts per cell table) for a 300 kVA UPS, 94% efficiency, power factor of 0.8, for a backup time of 15 minutes.

The UPS battery bus voltage is 480 V. The typical table is for 12 V batteries (six cells of 2 V each).

 

Solution:

Quantity of batteries per bank = 480/12 = 40 batteries

Number of cells per bank = 40 x 6 = 240 cells

Watt per cell = (VA x PF)/ (EFF x Number of Cells)

 

Watt per cell = (300*1000*0.8)/(0.94*240) = 1063 w/cell




Looking at the capacity in the table, we see that the required watt/cell is too much for one bank. However, various options are available, for example if we decided to use three banks in parallel:

Watt per cell (three banks in parallel) = 1063/3 = 354 w/cell

Select a S12V370(F) battery with watts per cell = 372

Total number of batteries required = 40 (per bank) x 3 (banks) = 120


Example#5:

Determine the battery required for a 20 kVA UPS operating at full load with an efficiency of 86%, a load power factor of 0.8 and no additional DC loads. The UPS is a 130 VDC system requiring 60 cells of lead acid batteries and requiring 30 minutes of back-up time.

Solution:

W / cell = (VA x PF)/ (EFF x Number of Cells)= (20,000 x 0.8) / (0.86 x60) = 310 W/Cell = 0.310 KW/cell

The UPS manufacturer will also recommend the battery be discharged to a specific end voltage per cell. For a 60 cell lead acid battery, this will normally be 105V per bank or 1.75 volts/cell.

Utilizing the battery manufacturer’s supplied information, such as that in below table for this 20 kVA UPS, 60 cells of from the type CX-11 are required which will supply 19.4 kW (0.324kW x 60 cells = 19.4 KW) for 30 minutes




 

 

 

 

Method#2: Watts per Bank Method

 

In this method, Normally information supplied for lead acid batteries from manufacturers is in the form of kilowatts per bank tabulated for various back-up times. The required [Watts] per bank are given by:

W/bank = W/cell * Number of cells per bank

 

Example#6:

A 30 KVA UPS operating at 20KVA/16KW Load with an efficiency of 93%, a load power factor of 0.8 and no additional DC loads. The UPS is a 432 VDC system with 216 cells of lead acid batteries and requiring 20 minutes of back-up time.

The typical table is for 12 V batteries (six cells of 2 V each).

Calculate the nos. of battery banks/strings required.

 

Solution:

Quantity of batteries per bank = 432/12 = 36 batteries

Number of cells per bank = 36 x 6 = 216 cells

Calculated W/cell = (VA x PF)/ (EFF x Number Of Cells) = (30000 x 0.8) /(0.93 x 216) = 79.649 W/cell

 

Calculated W/block = 79.649 W/cell x 6 = 477.894 W/block

Calculated W/String = 79.649 W/cell x 216 cells = 17,204.184 W/String

Or

Calculated W/String = 477.894 W/block x 36 block = 17,204.184 W/String

 

The UPS manufacturer will also recommend the battery be discharged to a specific end voltage per cell.

As per the manufacturer’s datasheet, this will normally be 378V per bank or = 378 V/216 cell = 1.75 volts/cell.

 


Utilizing the Fiamm Battery manufacturer supplied information, such as that in Figure 1, Select a FG20721 battery with watts per block = 119.4 w

Total number of batteries required = 17,204.184 / 119.4 = 144 battery

Nos, of strings required = 144 / 36 = 4

or

Required nos. of Strings = Calculated W/block / selected w/block = 477.894/119.4 = 4

 

Actual W/String = 119.4 w * 36*4 = 17,193.6 w

 

 

Autonomy Calculation as per Fiamm battery manufacturer supplied information at constant power discharge of 17,204.184 W:

 

T1 = 20 min (As per Column 5 of figure-1: Fiamm Battery Discharge Data) &

T2 = ?? (Actual obtained Back-up Time)

 

I) As per supplied information: W α 1/ T1 => 119.4 W α 1 /20 minute

 

II) As per demand load calculation: W α 1/ T2 => 119.4 W α 1 / T2 minute

 

Hence, (119.4 W α 1 /20 minute = 119.4 W α 1/ T2 minute)

then (119.4 x 20 = 119.4 x T2)

T2 = 119.4 x 20/119.4  = 2388/119.4 = 20 Minutes (Required Backup)

 

 

Example#7:

 

A 15 mins backup on a 500KVA UPS with an output power factor of 0.9 and following data:

 

UPS Rating (KVA)

500KVA

Specified by Customer or Consultant

Actual Load on UPS (KVA)

500KVA

Specified by Customer or Consultant

Output Power Factor

0.8

Specified by Customer or Consultant

Inverter Efficiency (n)

95%

Based on UPS Manufacturer’s data

No of Batteries

50 Nos

Based on UPS Manufacturer’s data

End Cell Voltage (ECV)

1.75V

Specified by Customer or Consultant

Backup time required (in mins)

10 mins

Specified by Customer or Consultant

Ageing Factor

1.25

Specified by Customer or Consultant

Design Margin

1

Specified by Customer or Consultant

Temperature Correction Factor

1

Specified by Customer or Consultant

Calculate the nos. of battery banks/strings required.

 

Solution:

 

Step 1:

Arrive UPS output power rating in watts = UPS output in volts-amperes × power factor

= 500 X 0.8 KW = 400KW

Step 2:

Arrive the nominal battery load in W

Nominal battery load in W = UPS output power in kW X1000 / Inverter efficiency = Answer of Step 1 / Inverter efficiency = 400 X 1000 / 0.95 = 421053 W

 

Step 3:

Arrive the nominal battery load in W per Battery

Nominal battery load in W/Battery = Answer of step 2 / No of Batteries = 421053 W / 50 = 8421 W/Battery

 

Step 4:

Arrive at the adjusted battery power required by taking into consideration design margin,

ageing factor and TCF (Temperature correction factor)

Adjusted nominal battery load in W/Battery = Answer of Step 3 X Design Margin X Ageing Factor X TCF

= 8421.05 X 1 X 1.25 X 1

=10526 W/Battery

 

As the maximum available AH is 200AH Battery in 12V SMF VRLA battery, we need to parallel multiple strings of battery to achieve the desired backup time.

 

Step 5:

 

No of strings required = Watts/Per battery required (Answer of step 4) / Watts the battery can deliver (from battery manufacturer datasheet)

A 160AH battery can deliver 3552 W at end cell voltage of 1.75V/Cell for 10 mins

= 10526 W / 3552W = 2.96 strings = 3 strings

 

Hence in this scenario, 3 strings of 160AH battery with 50 battery in each string will provide 10 mins backup at end cell voltage of 1.75V/Cell.

 

 

 

 

Method#3: Amperes per Cell

 

Long term discharge lead acid batteries and most nickel cadmium batteries are sized using charts expressed in available amps for specified periods of time. The required [Amperes] per cell is:

 

Ampere per cell = AS + (VA x PF)/ (EFF x Vdc)

 

Where:

AS = Additional loads expressed in amperes

VA = VA of the load or UPS

PF = Power factor of load

EFF = Efficiency of the UPS Inverter

Vdc = Average discharge voltage

 

Average Battery Voltage

Battery voltage varies in use - starting high and then decreasing to it's end of discharge voltage.  Taking into account this variation, makes calculation more complicated. 

More often, an average voltage value is taken and calculations based on this. If unsure about what the average value to use, then the end of discharge voltage could be used (as this is on the safe side).

For these calculations, it is recommended that one calculate battery current based upon 104% of the final end voltage of the battery bank. For example, 60 cells with an end voltage of 1 .75V/cell will equal 105V/Bank. Consequently, 104% of 105V equals 109V. An average current will be calculated at this voltage.

 

Example#8:

Determine the battery required for a 20 kVA operating at full load with an efficiency of 86%, a load power factor of 0.8 and 30 amps of additional DC loads. The UPS is 130 VDC system requiring 92 cells of nickel cadmium batteries and requiring three hours of back-up time.

 

Solution:

 

Utilizing the following formula:

Ampere per cell = AS + (VA x PF)/ (EFF x Vdc)

 

 

DC Amps = 30+ (20 x 0.8 x 1000) / (0.86 x 109) = 200.68 Amps

 

The UPS manufacturer has recommended an end voltage of 105V per bank or 1.14V per cell for the 92 cell bank.

 

Using below Figure  for this 20 kVA UPS and additional 30 amp DC load, 92 cells of HB705P are required which will supply 213 amps for three hours.

 


 

 

In the next Article, we will explain the IEEE Methods for battery sizing calculations. So, please keep following.

 

Subject Of Pervious Article

Article

Applicable Standards for UPS Systems

  • What is a UPS?
  • Why do we need a UPS?
  • UPS Rating

Classification of UPS:

1-Voltage range,

2-No. of phases,

3- Mobility,

4- Technological design,

 

Classification and Types of UPS – Part One


5- Physical Size/capacity,

6- Form factor/ configurations:

6.1- “N” System Configuration

Classification and Types of UPS – Part Two


6.2- “N+1” System Configuration, which includes:

  • Isolated Redundant Configuration (N +1)
  • Parallel Redundant Configuration (1+1)
  • Parallel Redundant Configuration (N +1)
  • Parallel Redundant Configuration (N +2) and so on

6.3- Parallel Redundant with Dual Bus Configuration (N+1 or 1+1)


Classification and Types of UPS – Part Three


 

6.4- Parallel Redundant with STS Configuration

  • Parallel Redundant Configuration (1+1) + STS
  • Parallel Redundant Configuration (N+1) + STS

6.5- System plus System 2(N+1), 2N+2, [(N+1) + (N+1)], and 2N

 

Classification and Types of UPS – Part Four


 

 

7- According to UPS Topology

7.1 Off-line or Standby UPS,

7.2 Line Interactive UPS,

7.3 Standby-Ferro UPS,

7.4 Online Double Conversion UPS,

7.5 The Delta Conversion On-Line UPS.

Classification and Types of UPS – Part Five

 

 

 

8- According to UPS Distribution Architecture

8.1 Centralized UPS Configuration,

8.2 Distributed (Decentralized) UPS Configuration,

8.2.1 Distributed UPS-Zonewise Configuration

8.3 Hybrid UPS Configuration.

Conventional (Monolithic) Vs Modular UPS System:

  • Deploy UPSs in parallel,
  • Deploy UPSs in Series,
  • Use modular UPS products. 

Classification and Types of UPS – Part Six


 

Three Basic Configurations Of Mains And Bypass For A UPS System:

  • Single mains,
  • Single mains without bypass,
  • Dual mains.

9-According to Use of transformers with the UPS

  • Transformer based,
  • Transformer less UPS,
  • Transformer less UPS with external input/ output transformer.

Classification and Types of UPS – Part Seven


 

 

Transformer Arrangements in Practical UPS Systems:

1-Transformer options for the “single mains” configuration

2-Transformer Options for the “Dual Mains” Configuration

Classification and Types of UPS – Part Eight


 

3- Transformer options for “single mains without bypass”

Classification and Types of UPS – Part Nine

Components of Online Double Conversion UPS:

1- Rectifier,

2- Inverter,

3- Energy Storage system:

3.1 Battery

Components of Online Double Conversion UPS– Part One


 

 

3.1.1 Battery Configurations

  • Serial Strings,
  • Parallel Strings.

3.1.2 Battery Size and Location

3.1.3 Battery Transition Boxes

3.1.4 Battery Monitoring

3.2 Energy Storage System – Flywheel

3.3 Energy Storage system – Super Capacitors

3.4 Hydrogen Fuel Cells

4- Static switch

Earthing Principles of UPS Systems

Components of Online Double Conversion UPS – Part Two


 

Evaluation Criteria for Selecting an UPS:

Step#1: Determining the need for an UPS,

Step#2: Determining the purpose(s) of the UPS,

Step#3: Determining the power requirements,

Step#4: Selecting the type of UPS,

Step#5: Determining if the safety of the selected UPS is acceptable,

Step#6: Determining if the availability of the selected UPS is acceptable,

Step#7: Determining if the selected UPS is maintainable, and

Step#8: Determining if the selected UPS is affordable.

 

Evaluation Criteria for Selecting an UPS-Part One


 

 

 

Example: Selecting an Uninterruptible Power Supply (UPS)

UPS System Ratings and Service Conditions

First: from IEC 60146-4

Second: according to American standards

Evaluation Criteria for Selecting an UPS-Part Two


 

The UPS sizing calculations steps:

Step#1: List All the UPS Loads

Step#2: List for Each Equipment/Load, the Voltage, Number of Phases, and Frequency

Step#3: List the KVA for Each Equipment/Load

Step#4: Determine The UPS Voltage, Number Of Phases, and Frequency.

Step#5: Segregate the Loads (Non-Motor Loads & Motor Loads)

Step#6: Determining Load Power Factor and KW Demand

Step#7: Determining Load Inrush Current/KVA.

Step#8: Determine Loads’ Sequence of Operation

Step#9: Apply the Derating Factors (If Any)

Step#10:  Calculate the Design UPS Load KVA

 

Stationary UPS Sizing Calculations – Part One


 

 

1 comment: