In the previous article “Classification and Types of UPS – Part Two”, we stated that according to the Form factor/ configurations, the UPS Systems have five famous configurations, which are:
1- “N” System Configuration
2- “N+1” System Configuration, which includes:
- Isolated Redundant Configuration (N +1)
- Parallel Redundant Configuration (1+1)
- Parallel Redundant Configuration (N +1)
- Parallel Redundant Configuration (N +2) and so on
3- Parallel Redundant with Dual Bus Configuration (N+1 or 1+1)
4- Parallel Redundant with STS Configuration
- Parallel Redundant Configuration (1+1) + STS
- Parallel Redundant Configuration (N+1) + STS
5- System plus System
2(N+1), 2N+2, [(N+1) + (N+1)], and 2N
We explained the first three UPS System
Configurations and today, we will continue explaining the other configurations
of UPS Systems.
4- Parallel
Redundant with STS Configuration |
Parallel
Redundant with STS Configuration, sometimes called Distributed Redundant Configuration, has many
sub-Configurations included under it like:
|
Important definitions: 1-
Single Point of Failure: An
element of the electrical distribution system that at some point will cause downtime,
if a means to bypass it is not developed in the system. An N configuration
system is essentially comprised of a series of single points of failure.
Eliminating these from a design is a key component of redundancy. 2-
Static Transfer Switch (STS): An
STS has two inputs and one output. It typically accepts power from two different
UPS systems, and provides the load with conditioned power from one of them.
Upon a failure of its primary UPS feeders the STS will transfer the load to
its secondary UPS feeder in about 4 milliseconds, and thus keep the load on
protected power at all times. This technology was developed in the early 1990’s,
and is commonly used in distributed redundant configurations. |
1- Parallel Redundant
Configuration (1+1) + STS The
distributed redundant configuration (1+1), see Fig-1, utilizes two standalone
configured UPS systems in conjunction with two stand-alone Static transfer
switches. Fig.1- Parallel Redundant Configuration (1+1) + STS In
normal operation, both units are designed to carry 50% of the critical load,
and have 50% reserve capability to support the load on the other bus in the
event the UPS feeding the other load bus encounters an operational problem.
This allows complete independence and total isolation of the two UPS units
from each other, facilitates separate output load buses, and eliminates the
possibilities of single point failures either due to faults on the load side
or because of faults within the two units. The result is a configuration that
allows both critical load buses to be automatically fed from either the
dedicated bus unit or the redundant unit. The failure of UPS #1 would cause External Static Switch #1 to feed that system’s load from UPS #2. Similarly, the failure of UPS #2 would cause External Static Switch #2 to feed that systems load from UPS #1. Note, a common bypass feed, i.e. from the same bypass source, is necessary to ensure that the output of the two systems will be synchronized, and to allow availability of unrestricted fault clearing power.
|
Important definitions: 1-
Concurrent Maintenance: The ability to completely shut down any particular electrical component, or subset of components, for maintenance or routine testing without requiring that the load be transferred to the utility source. 2-
Single-Corded Loads When the environment consists of single-corded equipment, each piece of IT equipment can only be fed from a single STS or rack mount transfer switch. Bringing the switch closer to the load is a prerequisite for high availability in redundant architectures as demonstrated in APC White Paper #48. Placing hundreds of single-corded devices on a single large STS is an elevated risk factor. Deploying multiple smaller switches feeding smaller percentages of the loads would mitigate this concern. In addition, distributed rack-mount transfer switches do not exhibit the failure modes that propagate faults upstream to multiple UPS system as is the case with larger STS. For this reason, the use of rack-based transfer switches is becoming more common, particularly when only a fraction of the load is single-corded. APC White Paper #62, “Powering Single-Corded Equipment in a Dual Path Environment” discusses the differences between STS and rack mount transfer switches in greater detail. 3- Dual-Corded Loads: Dual-corded loads are becoming more the standard as time progresses, therefore the use of an STS is not necessary. The loads can simply be connected to two separate PDUs which are fed from separate UPS systems. 4- Multiple Source Synchronization: When STS units are employed in a data center, it is important for the two UPS feeds to be in synchronization. Without synchronization control it is possible for UPS modules to be out of phase, especially when they are running on battery. |
2- Parallel Redundant
Configuration (N+1) + STS The
distributed redundant configuration (N+1),
see Fig-2, utilizes three or more UPS modules with independent
input and output feeders. The independent output buses are connected to the
critical load via multiple PDUs and STS. From the utility service entrance to the UPS, a distributed
redundant design and a system plus system design (discussed in the next
section) are quite similar. Both provide for concurrent maintenance, and
minimize single points of failure. The major difference is in the quantity of
UPS modules that are required in order to provide redundant power paths to
the critical load, and the organization of the distribution from the UPS to
the critical load. As the load requirement, “N”, grows the savings in
quantity of UPS modules also increases. Figures 2 and 3 illustrate a 300 kW load with two different distributed redundant design concepts. Concept#1: Fig.2 uses three UPS modules in a distributed redundant design
that could also be termed a “catcher system”. In this configuration, module 3
is connected to the secondary input on each STS, and would “catch” the load upon
the failure of either primary UPS module. In this catcher system, module 3 is
typically unloaded. Concept#2: Fig.3
shows a distributed redundant design with three STS and the load evenly
distributed across the three modules in normal operation. The failure on any
one module would force the STS to transfer the load to the UPS module feeding
its alternate source. Evident
in both of these one lines is the difference between distributing power to
dual-corded loads and single-corded loads. The dual-corded loads can be fed
from two STS units while the single-corded loads can only be fed from a
single STS. For the single-corded loads the STS becomes a single point of
failure. Fig.3- Distributed Redundant UPS Configuration
As the quantity of single-corded loads in data centers today are becoming fewer and fewer it is becoming more practical, and less costly to apply multiple, small, point of use transfer switches close to the single corded loads. In cases with 100% dual-corded loads this configuration could be designed without STS units. Distributed redundant systems are usually chosen for large complex installations where concurrent maintenance is a requirement and many or most loads are single corded. Savings over 2N also drive this configuration. Other industry factors that drive distributed redundant configurations are as follows: The primary weakness of this design is the use of static transfer switches. These devices are very complex and have some unexpected failure modes, the worst of which is that they can fail in a way that causes the two inputs to short circuit to each other. In this type of event the STS can become a single point of failure since it can cause two UPS to drop the load simultaneously. The failure of a STS can propagate upstream and affect the entire system operation. For this reason the system + system design described in the following section has greater fundamental availability, particularly if the load devices have dual cord redundant powering capability. There are many options in an STS configuration and several grades of STS reliability on the market to consider. In this configuration, the STS is ahead of the PDU (on the 480 volt side). This is a common application. Many engineers believe, justifiably so, that placing the STS on the 208 volt side of two PDUs is a more reliable application. This is a much more expensive application than the 480 volt STS. A solution to prevent an out of phase transfer is to install a
synchronization unit between the two UPS systems, allowing them to
synchronize their AC output. This is especially critical when the UPS modules
have lost input power and are on battery operation. The synchronization unit
makes sure that all UPS systems are in sync at all times, so during a
transfer in the STS, the power will be 100% in phase, thus preventing an out
of phase transfer and possible damage to downstream equipment. Of course,
adding a synchronization unit between independent UPS systems allows for the
possibility of a common mode failure, or failure that can simultaneously drop
all UPS systems. Advantages:
Disadvantages:
|
5- System
plus System Redundant |
System plus System, Multiple Parallel Bus, Double-Ended, 2(N+1), 2N+2, [(N+1) + (N+1)], and 2N are all nomenclatures that refer to variations of this configuration. With this design, it now becomes possible to create UPS systems that may never require the load to be transferred to the utility power source. These systems can be designed to wring out every conceivable single point of failure. However, the more single points of failure that are eliminated, the more expensive this design will cost to implement. Most large system plus system installations are located in
standalone, specially designed buildings. It is not uncommon for the
infrastructure support spaces (UPS, battery, cooling, generator, utility, and
electrical distribution rooms) to be equal in size to the data center
equipment space. This is the most reliable, and most expensive, design in the
industry. It can be very simple or very complex depending on the engineer’s
vision and the requirements of the owner. Although a name has been given to this
configuration, the details of the design can vary greatly and this, again, is
in the vision and knowledge of the design engineer responsible for the job. Fig.4- System plus System Redundant
The 2(N+1) variation of this configuration, as illustrated in Fig.4,
revolves around the duplication of parallel redundant UPS systems. Optimally
these UPS systems would be fed from separate switchboards, and even from
separate utility services and possibly separate generator systems. The
extreme cost of building this type of facility has been justified by the
importance of what is happening within the walls of the data center and the
cost of downtime to operations. Many of the world’s largest organizations
have chosen this configuration to protect their critical load. The
cost of this configuration is affected by how “deep and wide” the design
engineer deems is necessary to take the system duplication efforts to meet
the needs of the client. The fundamental concept behind this configuration
requires that each piece of electrical equipment can fail or be turned off
manually without requiring that the critical load be transferred to utility
power. Common in 2(N+1) design are bypass circuits that will allow sections
of the system to be shut down and bypassed to an alternate source that will
maintain the redundant integrity of the installation. An
example of this can be seen in Fig.4: the tie circuit between the UPS input
panelboards will allow one of the utility service entrances to be shut down
without requiring one of the UPS systems to be shut down. In a 2(N+1) design,
a single UPS module failure will simply result in that UPS module being
removed from the circuit, and its parallel modules assuming additional load. In
this example illustrated in Fig.4, the critical load is 300 kW, therefore the
design requires that four 300 kW UPS modules be provided, two each on two
separate parallel buses. Each bus feeds the necessary distribution to feed
two separate paths directly to the dual-corded loads. The single-corded load,
illustrated in Figure 6, shows how a transfer switch can bring redundancy
close to the load. However, Tier IV power architectures require that all
loads to be dual-corded. Companies
that choose system plus system configurations are generally more concerned
about high availability then the cost of achieving it. These companies also
have a large percentage of dual-corded loads. In addition to the factors
discussed in the distributed redundant section, other factors that drive this
design configuration are as follows: 1- Hardening: Designing a system, and a building, that is immune to the ravages of nature, and is immune to the types of cascading failures that can occur in electrical systems. The ability to isolate and contain a failure; for example, the two UPS systems would not reside in the same room, and the batteries would not be in the same room with the UPS modules. Circuit breaker coordination becomes a critical component of these designs. Proper Circuit breaker coordination can prevent short circuits from affecting large portions of the building. Hardening a building can also mean making it more immune to events such as hurricanes, tornadoes, and floods, as might be necessary depending on where the building is. For example designing the buildings away from 100 year flood plains, avoiding flight paths overhead, specifying thick walls and no windows all help to create this immunity. 2- Static Transfer Switch (STS): With the advent of dual-cord capable IT equipment,
these devices along with their undesirable failure modes can be eliminated
with a significant increase in system availability. 3- Single-Corded Loads: To take full advantage of the redundancy benefits of
system plus system designs, single-corded loads should be connected to
transfer switches at the rack level. Advantages:
Disadvantages:
|
Choosing the Right Configuration |
Important definitions: 1- Reliability: Evaluates a configuration’s capability to maintain conditioned power to the load. 2-
Availability: It is the estimated percentage of time that electrical power will be online and functioning properly to support the critical load. 3-
Complexity: Looks at the complexity of the configuration and the potential for single point failures. 4- Maintainability: The system configuration must allow for concurrent maintenance of all power system components – supporting the load with part of the UPS system while other parts are being serviced. 5- Functionality: The system configuration must be able to protect the critical load from a full range of power disturbances without transferring the critical load to external power sources, i.e. batteries or alternate power sources. 6- Tiers: All UPS systems (and electrical distribution equipment) require
regular intervals of maintenance. The availability of a system configuration
is dependent on its level of immunity to equipment failure, and the inherent
ability to perform normal maintenance, and routine testing while maintaining
the critical load. |
The considerations for selecting the appropriate configuration
are: 1- Cost / Impact of downtime: How much money is flowing through the company every minute, how
long will it take to recover systems after a failure? The answer to this
question will help drive a budget discussion. If the answer is $10,000,000 /
minute versus $1,000,000 / hour the discussion will be different. As the configuration
goes higher on the scale of availability, the cost also increases. Table-1
shows the scale of availability and cost for different UPS Configurations. 2- Risk Tolerance: Companies that have not experienced a major failure are
typically more risk tolerant than companies that have not. Smart companies will
learn from what companies in their industry are doing. This is called
“Benchmarking” and it can be done in many ways. The more risk intolerant a company is, the more internal drive their will be to have more reliable operations, and disaster recovery capabilities. 3- Availability requirements: How much downtime can the company withstand in a typical year? If the answer is none, then a high availability design should be in the budget. However, if the business can shut down every night after 10 PM, and on most weekends, then the UPS configuration wouldn’t need to go far beyond a parallel redundant design. Every UPS will, at some point, need maintenance, and UPS systems do fail periodically, and somewhat unpredictably. The less time that can be found in a yearly schedule to allow for maintenance the more a system needs the elements of a redundant design. 4- Types
of loads (single vs. dual-corded): Dual-corded loads provide a real opportunity for a design to leverage a redundant capability, but the system plus system design concept was created before dual-corded equipment existed. The computer manufacturing industry was definitely listening to their clients when they started making dual-corded loads. The nature of loads within the data center will help guide a design effort, but are much less a driving force than the issues stated above. 5- Budget: The cost of implementing a 2(N+1) design is significantly more, in every respect, than a capacity design, a parallel redundant design, or even a distributed redundant. As an example of the cost difference in a large data center, a 2(N+1) design may require thirty 800 kW modules (five modules per parallel bus; six parallel busses). A distributed redundant design for this same facility requires only eighteen 800 kW modules, a huge cost savings. The
flowchart illustrated in Fig.5 is a useful starting point for selecting the
right UPS system design configuration for a particular application. By
following the questions in the flowchart, the appropriate system can be
identified. Note: For
designs with no or little redundancy of components, periods of downtime for
maintenance should be expected. If this downtime is unacceptable, then a
design that allows for concurrent maintenance should be selected. |
In the next Article, I will continue explaining other Classifications of
UPS Systems like:
7- Topology,
8- Distribution Architecture,
9- Use of transformers.
So, please
keep following.
Subject Of Pervious Article |
Article |
Applicable Standards for UPS Systems
|
Classification and Types of
UPS – Part One |
5- Physical Size/capacity, 6- Form factor/ configurations: 6.1- “N” System
Configuration |
Classification and Types of UPS – Part Two |
6.2- “N+1” System Configuration, which includes:
6.3- Parallel Redundant
with Dual Bus Configuration (N+1 or 1+1) |
Classification and Types of
UPS – Part Three |
No comments:
Post a Comment