Second: Consultation phase
- The lightning protection designer
should hold relevant technical consultations with all parties involved in the
design and construction of the structure, including the owner of the
structure.
- Particular areas of
responsibility for the total installation of the LPS should be defined by the
LPS designer in conjunction with the architect, electrical contractor,
building contractor, the LPS installer (LPS supplier) and, where relevant, a
historical adviser and the owner or owner’s representative.
- Regular consultation between LPS
designers and installers, architects and builders is essential in order to
achieve the best result at minimum cost.
- The clarification of
responsibility for the various parties involved in the management of the
design and construction of the LPS is of particular importance. An example
might be where the waterproofing of the structure is punctured by roof-mounted
LPS components or by earth electrode connection conductors made below the
structure foundation.
1- Technical consultations with Architect
Agreement should be reached with
the architect on the following items:
- Routing of all LPS conductors;
- Materials for LPS components;
- Details of all metal pipes,
gutters, rails and similar items;
- Details of any equipment,
apparatus, plant installations, etc. to be installed on, within or near the
structure which may require the moving of installations or may require
bonding to the LPS because of the separation distance. Examples of
installations are alarm systems, security systems, internal telecommunication
systems, signal and data processing systems, radio and TV circuits;
- the extent of any buried
conductive service which could affect the positioning of the earth
termination network and be required to be placed at a safe distance from the
LPS;
- The general area available for
the earth-termination network;
- The extent of the work and the
division of responsibility for primary fixings of the LPS to the structure.
For example, those affecting the water tightness of the fabric (chiefly
roofing), etc;
- conductive materials to be used
in the structure, especially any continuous metal which may have to be bonded
to the LPS, for example stanchions, reinforcing steel and metal services
either entering, leaving, or within the structure;
- The visual impact of the LPS;
- The impact of the LPS on the
fabric of the structure;
- The location of the connection
points to the reinforcing steel, especially where they penetrate external
conductive parts (pipes, cable shields, etc.);
- The connection the LPS to the LPS
of adjacent buildings.
2- Technical consultations with Electronic system and
external antenna installers
Agreement with the electronic
system and antenna installer should be reached on the following items:
- The isolating or bonding of
aerial supports and conductive shields of cables to the LPS;
- The routing of aerial cables and
internal network;
- Installation of surge protective
devices.
3- Technical consultations with Builder and installer
Agreement on the following items
should be reached between the builder, installer, and those responsible for
construction of the structure and its technical equipment:
- The form, position and number of
primary fixings of the LPS to be provided by the builder;
- Any fixings provided by the LPS
designer (or the LPS contractor or the LPS supplier) to be installed by the
builder;
- The position of LPS conductors to
be placed beneath the structure;
- whether any components of the LPS
are to be used during the construction phase, for example the permanent
earth-termination network could be used for earthing cranes, hoists and other
metallic items during construction work on the site;
- For steel-framed structures, the
number and position of stanchions and the form of fixing to be made for the
connection of earth-terminations and other components of the LPS;
- Whether metal coverings, where
used, are suitable as components of the LPS;
- The method of ensuring the
electrical continuity of the individual parts of the coverings and their
method of connecting them to the rest of the LPS where metal coverings are
suitable as components of the LPS;
- the nature and location of
services entering the structure above and below ground including conveyor
systems, television and radio aerials and their metal supports, metal flues
and window cleaning gear;
- Coordination of the structure's
LPS earth-termination system with the bonding of power and communication services;
- the position and number of flag
masts, roof-level plant rooms, for example lift motor rooms, ventilation,
heating and air-conditioning plant rooms, water tanks and other salient
features;
- the construction to be employed
for roofs and walls in order to determine appropriate methods of fixing LPS
conductors, specifically with a view to maintaining the water tightness of
the structure;
- The provision of holes through
the structure to allow free passage of LPS down conductors;
- The provision of bonding connections
to steel frames, reinforcement bars and other conductive parts of the
structure;
- The frequency of inspection of
LPS components which will become inaccessible, for example steel reinforcing
bars encapsulated in concrete;
- The most suitable choice of metal
for the conductors taking account of corrosion, especially at the point of
contact between dissimilar metals;
- Accessibility of test joints,
provision of protection by non-metallic casings against mechanical damage or
pilferage, lowering of flag masts or other movable objects, facilities for
periodic inspection especially for chimneys;
- The preparation of drawings
incorporating the above details and showing the positions of all conductors
and main components;
- The location of the connection
points to the reinforcing steel.
4- Technical consultations with Electrical designer
Agreement on the following items
should be reached between the builder, installer, and those responsible for
construction of the structure and its technical equipment:
- The proper use of foundation
steelwork for the purpose of forming an effective earth-termination may well
be impossible once construction work on a site has commenced. Therefore, soil
resistivity and the nature of the earth should be considered at the earliest
possible stage of a project. This information is fundamental to the design of
an earth termination system and may influence the foundation design work for
the structure. Soil resistivity tests should take into consideration the seasonal
variations of soil resistivity.
- During the completion of the
basic electrical design of the LPS, the use of suitable conductive parts of
the structure should be considered as natural components of the LPS to
enhance or act as essential components of the LPS.
- The use of metal reinforcing,
such as steel-reinforced concrete, as lightning protection conductors
requires careful consideration, and knowledge of the national construction
standards applicable to the structure to be protected. The steel skeleton of
reinforced concrete may be used as LPS conductors or may be used as a
conductive shielding layer to reduce the electromagnetic fields generated by
lightning in the structure as the lightning currents are conducted through an
isolated LPS. This LPS design makes protection easier, in particular for
special structures containing extensive electrical and electronic
installations.
5- Technical consultations with Mechanical designer
The lightning protection designer
should consult with the persons responsible for the structure on mechanical
design matters, following the completion of the electrical design, for the
following points:
- The minimum size of lightning
protection components for the various parts of the LPS.
- The materials used for the LPS
components.
- The lightning protection designer
or installer should predict the temperature rise and mechanical strength of
lightning conductors and other components, such as rods and clamps under
discharge conditions and dimension the conductors accordingly.
- When excessive temperature rise
is a concern for the surface on which the components are to be attached
(because it is flammable or has a low melting point), either larger conductor
cross-sections should be specified or other safety precautions should be
considered, such as the use of stand-off fittings or the insertion of
fire-resistant layers.
- The LPS designer should identify
all corrosion problem areas and specify appropriate measures.
- The corrosion effects on the LPS
may be reduced either by increases in material size, by using corrosion
resistive components, or by taking other corrosion protection measures.
- The LPS designer and LPS
installer should specify conductor fasteners and fixtures which will
withstand the electrodynamic forces of lightning current in the conductors
and also allow for the expansion and contraction of conductors due to the
increase in temperature that occurs.
Notes to Consultation Phase:
- In the design and construction
stages of a new structure, the LPS designer, LPS installer and all other
persons responsible for installations in the structure or for regulations
pertaining to the use of the structure (e.g. purchaser, architect and
builder) should be in consultation regularly.
- In the design and construction
stages of an LPS for an existing structure, consultations should be held as
far as reasonably practical with the persons responsible for the structure,
its use, installations and incoming services.
- The consultations may have to be
arranged through the owner, the building contractor of the structure or their
appointed representative.
- Regular consultations between the
involved parties should result in an effective LPS at the lowest possible
cost. For example, the coordination of LPS design work with construction work
will often do away with the need for some bonding conductors and reduce the
length of those which are necessary. Building costs are often reduced
substantially by the provision of common routes for various installations
within a structure.
- Consultation is important
throughout all stages of the construction of a structure as modifications to
the LPS may be required due to changes in the structure design.
- Consultation is also necessary so
that arrangements can be agreed to facilitate inspection of the parts of the
LPS which will become inaccessible for visual control after the structure is
completed. In these consultations, the location of all connections between
natural components and the LPS should be determined. Architects are normally
available to arrange and coordinate consultation meetings for new building
projects.
|
No comments:
Post a Comment