Today, we will continue explaining in detail the applicable procedures for Generators Sizing Calculations for Existing and New Installations.
| 
   
Fourth: Applicable Procedures For Generators Sizing
  Calculations 
 | 
 
| 
   
In the previous Article “Generators
  Sizing Calculations – Part Ten”, we list the required steps for generator set sizing
  calculation and we indicate that the required steps will differ according to
  the type of the installation; new or existing as follows: 
For
  Existing Installations 
the required steps for generator
  set sizing calculation will be as follows: 
Step#1:
  Determine the Required Generator(S) Set Rating, 
Step#2:
  Assign the System Voltage and Phase, 
Step#3: Segregate the Loads, 
Step#4: Match
  the System to the Load Profile, Calculate the Required Number of
  Generator Sets and Paralleling Requirement, 
Step#5: Calculate the peak load of the
  installation  
Step#6: Check for transients or harmonics by using power analyzers and de-rate the
  peak load value. 
Step#7: Adjust the Generator
  Rating According To
  Transient Voltage Dip, 
Step#8:
  Adjust the Generator Rating According To Site Conditions, 
Step#9: Adjust
  the Generator Rating According To Fuel Type, 
Step#10:
  Adjust the Generator Rating According To Future
  Needs, 
Step#11: Adjust
  the Generator Rating According To Power Factor, 
Step#12: Calculate the Adjusted Generator
  Rating, 
Step#13: Select Generator Rating from
  Standard Sizes/Manufacturers Catalogs, 
Step#14:
  Assign Required
  Number Of Steps/Starting Sequence. 
For
  New Constructions 
the required steps for generator
  set sizing calculation will be as follows: 
Step#1:
  Determine the Required Generator(S) Set Rating, 
Step#2:
  Assign the System Voltage and Phase, 
Step#3: Segregate the Loads, 
Step#4: Match
  the System to the Load Profile, Calculate the Required Number of
  Generator Sets and Paralleling Requirement, 
Step#5: Calculate Connected Loads to Generator 
Step#6: Calculate
  Effective Load to Generator, 
Step#7: Adjust the Generator
  Rating According To
  Transient Voltage Dip, 
Step#8:
  Adjust the Generator Rating According To Site Conditions, 
Step#9:
  Adjust the Generator Rating According To Fuel Type, 
Step#10:
  Adjust the Generator Rating According To Future
  Needs, 
Step#11: Adjust
  the Generator Rating According To Power Factor, 
Step#12: Calculate the Adjusted Generator
  Rating, 
Step#13: Select Generator Rating from
  Standard Sizes/Manufacturers Catalogs, 
Step#14:
  Assign Required
  Number Of Steps/Starting Sequence. 
Now, we will explain in detail the
  above steps of Generators Sizing Calculations for Existing and New
  Installations. 
 | 
 
| 
   
Step#7: Adjust the Generator Rating According To Transient Voltage Dip 
 | 
 
| 
   
Generator Voltage Dip Calculation 
We
  have two methods to calculate/determine the Generator Voltage Dip as follows: 
 
1- By using equations 
 
 
Or by this equivalent equation: 
Notes: 
 
  | 
 
| 
   
The
  Maximum Allowable Voltage Dip 
The maximum allowable voltage dip is 30%.
   
Notes: 
 
The relation
  between the generator size and voltage dip% is shown in Fig.1: 
 | 
 
| 
   
If 
calculated
  voltage dip ˃ Maximum Allowable Voltage Dip 
You must increase the value of the
  generator effective load used in the calculation of the voltage dip. 
Then 
Generator
  KW adjusted  =
  K x Generator KW effective 
  
where factor K ˃1 by a percentage
  sufficient to minimize the voltage dip below the Maximum Allowable value 
Example: 
2000 kW
  @ 0.8 PF with X’D = 18.2% starts a 750 HP code F motor – What is the
  approximate voltage dip? 
Solution: 
Rated
  kVA = 2000 kW / 0.8 PF = 2500 KVA 
Starting
  kVA = 750 HP × 5.6 kVA / HP = 4200 KVA 
% dip =
  100 x (0.182) / (0.182 + (2500 / 4200)) = 23.4% 
Calculated
  voltage dip (23.4%) ˂ Maximum Allowable Voltage Dip (30%) 
Then
  the size of the selected generator is suitable for the application. 
 | 
 
| 
   
For more information about Transient
  Voltage Dip, please review our article” Generators
  Sizing Calculations – Part Six”. 
 | 
 
| 
   
Step#8: Adjust the Generator Rating According To Site Conditions 
 | 
 
| 
   
1- Ambient Temperature  
Where the temperature of the ventilating
  air to the generator exceeds 40°C (104°F), derating of the generator may be
  necessary. 
The de-rating percentage will differ from
  a manufacturer to another. However, an average de-rating percentage can be as
  follows: 
An engine’s power rating assumes a nominal
  altitude of less than 1000 feet, ambient temperature less than 104°F, and
  humidity less than 75%. Manufacturers detail the percentage reduction in
  available power for ambient conditions that exceed those assumed for the
  nominal rating. 
2-
  Altitude 
The higher the altitude, the lower the
  air density.  The altitude/temperature
  derating chart found in TMI can be used for proper derating information for
  generators and each specific engine. Figure
  .2 shows a sample engine TMI de-rate chart.
  (TMI: Technical Marketing Information). 
 | 
 
| 
   
Step#9: Adjust the Generator Rating According To Fuel
  Type 
 | 
 
| 
   
The
  selection of natural gas, diesel, or LPG fuel will affect generator set
  availability and sizing. Often, generator sets running on
  gas or LP must be oversized due to de-rating.  
The standard
  de-rating formula states that for every 1000 ft above sea-level, the following
  de-rating must be applied: 
  | 
 
| 
   
For more information about Site
  Conditions & Fuel Type selection, please review our article” Generators
  Sizing Calculations – Part Four”. 
 | 
 
| 
   
Step#10: Adjust the Generator Rating According To
  Future Needs 
 | 
 
| 
   
The customers’ future needs are to be
  taken into account when sizing the generator set. If the customer anticipates
  growth in their application due to increased volume or expanded needs, one of
  two design solutions can be applied: 
 
However, the projected load growth for
  any application should never be less than 10%. 
Table-1 shows typical load growth over a period of 10 years for various
  applications. 
 
Table-1: Load Growth over 10 Years for various
  applications 
 | 
 ||||||||||||||||
| 
   
Step#11: Adjust the Generator Rating According To
  Power Factor 
 | 
 
| 
   
Lower
  PFs require larger alternators or generator sets to properly serve the load.
  Usually Three-phase generator sets are rated for 0.8 PF loads and
  single-phase generator sets for 1.0 PF loads. 
For example, the following data in
  Table-2 for the Siemens AG type 1FC6 generators typify the de-rating
  factors for power factor that need to be applied. 
 
Table-2: Typical derating factors 
The following generator’s kW and
  kVA vs % lagging PF Chart can be used to determine the de-rating factor for lagging
  PF approximately: 
Fig.4: generator kW and
  kVA vs % lagging PF Chart 
 | 
 
| 
   
For more information about Power
  Factor de-rating rule, please review our article “Generators
  Sizing Calculations – Part Seven”. 
 | 
 
| 
   
Step#12: Calculate the Adjusted Generator Rating 
 | 
 
| 
   
From step#5, article “Generators
  Sizing Calculations – Part Twelve”,
  after application of demand and diversity factors to each category’s
  effective load, we calculate the Effective Load to Generator in step#6 in the
  same article as follows: 
Effective Load to
  Generator KW G-effective = Σ KW effective of all Load
  categories 
Based on this KW
  G-effective, we can make a preliminary selection of the generator.
   
Then, we must adjust the selected generator
  rating to comply with Transient
  Voltage Dip rule explained in step#7 to get at the end the KW G-accepted 
After
  that, Site Conditions de-rating factors, Fuel Type de-rating factor,
  Future Needs factor and Power Factor de-rating
  have to be applied as explained in steps# 8, 9, 10 & 11 respectively. 
Finally,
  we can say that the Adjusted Generator Rating KW G-adjusted can be
  calculated as follows: 
KW G-adjusted =
  KW G-accepted x K site conditions x K
  fuel type x K future needs x K pf 
 | 
 
| 
   
Step#13: Select Generator Rating from Standard
  Sizes/Manufacturers Catalogs 
 | 
 
| 
   
We can use the different Manufacturers Catalogs to assign
  the proper generator standard rating that will be next higher to KW G-adjusted
  calculated above. 
You can download the most famous Manufacturers Catalogs from the
  following links: 
After selecting the standard rating from
  above step, the following rules must be taken into consideration: 
 
 
Otherwise, you will need to move to the
  next higher size till you comply with the above two rules. 
 | 
 
| 
   
Step#14: Assign Required Number Of Steps/Starting
  Sequence 
 | 
 
| 
   
The
  Brake Mean Effective Pressure (BMEP) charts are used for load step analysis and for developing a
  starting sequence of a generator.  
Fig.5:
  BMEP Curve from TMI 
For example, Using Figure.1, the number of load steps needed for
  desired power can be determined.  
First, find the BMEP of the engine at
  rated speed; BMEP levels are shown for each rating in the performance data of
  the TMI (Technical Marketing Information).  
Second, compare the percentage of block
  load with BMEP Curve, we will have 3 cases: 
 
 
  | 
 
| 
   
For more information about The
  Brake Mean Effective Pressure (BMEP),
  please review our article “Generators Sizing Calculations –
  Part Nine”. 
 | 
 
In the next article, we will explain
the rules of thumbs and solved examples for Generators Sizing Calculations. So,
please keep following.
The
previous and related articles are listed in the below table:
| 
   
Subject of Previous Article 
 | 
  
   
Article 
 | 
 
| 
   
Glossary of Generators – Part One 
 | 
  |
| 
   
Glossary of Generators – Part Two 
 | 
  |
| 
   
First: Reasons for having on-site generators 
Second: Applicable performance standards for generator sets Third: Selection Factors Used For Generators Sizing Calculations 
  | 
  |
| 
   
Third: Selection Factors Used For
  Generators Sizing Calculations 
3- Location Considerations, 4- Fuel Selection Considerations, 5- Site Considerations,  | 
  |
| 
   
Third: Selection Factors Used For
  Generators Sizing Calculations 
6- Environmental Considerations, 7- System Voltage and Phase,  | 
  
  
 | 
 
| 
   
Third: Selection Factors Used For
  Generators Sizing Calculations 
8- Acceptable percent of voltage & frequency dip, 9- Acceptable duration of the voltage & frequency dip,  | 
  |
| 
   
Third: Selection Factors Used For
  Generators Sizing Calculations 
10- Percent And Type Of Loads To Be Connected – Part One  | 
  |
| 
   
10- Percent And Type Of Loads
  To Be Connected – Part Two 
 | 
  
  
 | 
 
| 
   
Third: Selection Factors Used For Generators Sizing
  Calculations 
11- Load step sequencing 
12- Future needs 
 | 
  |
| 
   
Fourth: Applicable
  Procedures For Generators Sizing Calculations 
1.1- Generator Load Factor 
1.2- Load Demand Factor 
1.3- Load Diversity Factor 
 | 
  |
| 
   
Fourth: Applicable
  Procedures For Generators Sizing Calculations 
Step#1: Determine the Required Generator(S) Set Rating, 
Step#2: Assign the System Voltage and
  Phase, 
Step#3:
  Segregate the Loads  
Step#4: Match the System to the Load
  Profile, Calculate the Required Number of Generator Sets and
  Paralleling Requirement, 
 | 
  |
| 
   
Fourth: Applicable
  Procedures For Generators Sizing Calculations 
Step#5-Existing Installations: Calculate the peak load of the
  installation  
Step#5-New Constructions: Calculate Connected Loads to Generator 
Step#6- Existing Installations: Check for transients or harmonics by using power analyzers and de-rate the
  peak load value. 
Step#6-New Constructions: Calculate
  Effective Load to Generator, 
 | 
  
| 
   Back To  | 
 








No comments:
Post a Comment